Posts

Showing posts from July, 2020

Check Concrete Foundation

Image
Check Concrete Foundation Concrete Foundation is extremely important to ensure the safety of the tank. Customers should construct a concrete base according to the design specification and the firmness of the site. Standard of Concrete Foundation 1) The required strength of the base concrete must be at least 180kg/cm² 2) Width of concrete foundation is more than 300mm. 3) Height of concrete foundationis 500mm. ※ 3M X 4M X 3M/Height DAEJOO ENG. CO.,LTD ​ Sky Seo (Managing Director) Website : www.daejoosmc.com Blog1 :  grp-water-tank.blogspot.com Blog2 :  blog.naver.com/biotank420 E-mail : biotank420@gmail.com Managing Director's Mobile / Whatsapp : +82-10-2758-7147 General Manager's Mobile / Whatsapp : +82-10-7741-8555

Installation of Internal Ladder

Image
Installation of Internal Ladder. Install the internal ladder and poles from the tank interior, after the connection of the roof panel block to side panel blocks. It is advisable to carry the internal ladder and poles into the tank before connecting the roof panel to the side panel block. Material is GRP DAEJOO ENG. CO.,LTD ​ Sky Seo (Managing Director) Website : www.daejoosmc.com Blog1 :  grp-water-tank.blogspot.com Blog2 :  blog.naver.com/biotank420 E-mail : biotank420@gmail.com Managing Director's Mobile / Whatsapp : +82-10-2758-7147 General Manager's Mobile / Whatsapp : +82-10-7741-8555

Installation of External Ladder

Image
Installation of External Ladder 1) The external ladder has support arms, which are bolted to the side panel and bottom panel flanges      with the bolts and nuts. 2) Material is HDG (Hot Dipped Galvanized) DAEJOO ENG. CO.,LTD ​ Sky Seo (Managing Director) Website : www.daejoosmc.com Blog1 :  grp-water-tank.blogspot.com Blog2 :  blog.naver.com/biotank420 E-mail : biotank420@gmail.com Managing Director's Mobile / Whatsapp : +82-10-2758-7147 General Manager's Mobile / Whatsapp : +82-10-7741-8555

Panel Quantity Formula

Image
Panel Quantity for the tank size For example 6mW * 7mL * 2mH 84 Ton (22193 Gallon) => 136㎡ Wall panel D grade (1m * 2m) : 26 unit Roof panel E grade (1m * 1m) : 41 unit Manhole Φ780 (1m * 1m) : 1 unit Bottom panel D grade (1m * 1m) : 41 unit Drainage panel C grade (1m * 1m) : 1 unit So we can make the Formula X mW * Y mL * Z mH If Z height is 1m, 1,5m, 2m, Wall panel (1m * Z m) : 2(X + Y) unit Roof panel (1m * 1 m) : (X x Y) - 1 unit Manhole (1m * 1m) : 1 unit Bottom panel (1m * 1m) : (X x Y) - 1 unit Drainage panel (1m * 1m) : 1 unit DAEJOO ENG. CO.,LTD ​ Sky Seo (Managing Director) Website : www.daejoosmc.com Blog1 :  grp-water-tank.blogspot.com Blog2 :  blog.naver.com/biotank420 E-mail : biotank420@gmail.com Managing Director's Mobile / Whatsapp : +82-10-2758-7147 General Manager's Mobile / Whatsapp : +82-10-7741-8555

Accessory Quantity for the tank size

Image
Accessory Quantity for the tank size Steel Skid (A) 1,140mm Steel Skid (A) 990mm Steel Skid (A) 2,120mm Steel Skid (A) 1,570mm Steel Skid (A) 1,990mm Steel Skid (B) 957mm Steel Skid (B) 994mm Steel Skid (B) 1063mm Steel Skid Joint 75*75 Steel Skid Joint 75*125 Steel Skid Bolt/Nut/Washer M14*45ℓ GI Steel Skid & Panel Joint Bolt M12*40ℓ GI Anchor Bolt Reinforcing Angle (55*950mm*3T) Reinforcing Angle (55*1,200mm*4T) External Ladder(HDG) Internal Ladder(GRP) PVC Roof Support Pipe 1m-2"Dia PVC Roof Support Pipe 1.5m-2"Dia PVC Roof Support Pipe 2m-2"Dia Coner Angle 1m - GI Coner Angle 1.5m - GI Coner Angle 2m - GI Coner Angle Bolt/Nut/Washer M10*35ℓ Sealant 120mm (Coner)- 1m Sealant 120mm (Coner) - 1.5m Sealant 120mm (Coner)- 2m Roof Panel Bolt M10*35ℓ - SS Side Panel Bolt M10*50ℓ - SS Bottom Panel Bolt M10*50ℓ - GI Tie rods ( Ø10.7 * 1,880mm ) Tie rods ( Ø10.7 * 2,880mm ) Rubber Capped Bolt Set M14*120ℓ Nut M12 - SS Plane Washer M12 - SS Spring Washer - SS For example(Pi

Panel Quantity for the tank size

Image
Panel Quantity for the tank size For example(Picture 3) 2.5mW * 4mL * 2mH  =  20 Ton (5284 Gallon) => 46㎡ Wall panel (1m * 2m) : 12 unit Wall panel (0.5m * 2m) : 2 unit Roof panel (1m * 1m) : 7 unit Roof panel (0.5m * 1m) : 4 unit Manhole (1m * 1m) : 1 unit Bottom panel (1m * 1m) : 7 unit Bottom panel (0.5m * 1m) : 4 unit Drainage panel (1m * 1m) : 1 unit DAEJOO ENG. CO.,LTD ​ Sky Seo (Managing Director) Website : www.daejoosmc.com Blog1 :  grp-water-tank.blogspot.com Blog2 :  blog.naver.com/biotank420 E-mail : biotank420@gmail.com Managing Director's Mobile / Whatsapp : +82-10-2758-7147 General Manager's Mobile / Whatsapp : +82-10-7741-8555

Water tank view and Parts name

Image
Water tank view and Parts name Panel Name 1. Side panel(1m x 2m) 2. Side panel(1m x 1m) 3. Manhole(Φ750) 4. Roof panel 5. Flange panel 6. Bottom panel 7. Drainage panel 8. Partition panel Parts Name a. Concrete Foundation b. Steel skid c. Drainage d. Outlet e. Corner flame f. Over flow g. Air vantilator h. External ladder i. Internal ladder j. Inlet k. Reinforcing angle l. Outer bracket m. Plate bar n. Inner Backet o. Tie rods DAEJOO ENG. CO.,LTD ​ Sky Seo (Managing Director) Website : www.daejoosmc.com Blog1 :  grp-water-tank.blogspot.com Blog2 :  blog.naver.com/biotank420 E-mail : biotank420@gmail.com Managing Director's Mobile / Whatsapp : +82-10-2758-7147 General Manager's Mobile / Whatsapp : +82-10-7741-8555