Posts

Showing posts from August, 2020

Assembly of side panel block

Image
Assembly of side panel block The assembly procedure is basically the same as that of the bottom panel block,  except for the following points. 1. Side panel blocks are equipped with unit panel reinforcing angles and reinforcing plates. 2. Side panel blocks consist of two different types of panels, one type for each tier as shown picture. Sky Seo (Managing Director) Website : www.daejoosmc.com Blog1 :  grp-water-tank.blogspot.com Blog2 :  blog.naver.com/biotank420 E-mail : biotank420@gmail.com Managing Director's Mobile / Whatsapp : +82-10-2758-7147 General Manager's Mobile / Whatsapp : +82-10-7741-8555

Installation Process

Image
Bio GRP sectional panel water tank Installation Process 1. Check Concrete Foundation 2. Check Steel Skid Base 3. Assembly of Bottom Panel Block 4. Setting of Bottom Panel block onto Steel Skid Base 5. Assembly of Side Panel Block 6. Assembly of Roof Panel Block 7. Installation of Roof Panel Block Support Pole 8. Installation of Internal Ladder 9. Nozzle Installation 10. Installation of External Ladder 11. Installation of Anchor Bolts 12. Cleaning in and out of the Water-Tank Sky Seo (Managing Director) Website : www.daejoosmc.com Blog1 :  grp-water-tank.blogspot.com Blog2 :  blog.naver.com/biotank420 E-mail : biotank420@gmail.com Managing Director's Mobile / Whatsapp : +82-10-2758-7147 General Manager's Mobile / Whatsapp : +82-10-7741-8555

Assembly of Bottom panel block

Image
Assembly of Bottom panel block Bottom Panel Block Assembly Sequence and Procedure 1) Attached the sealing tape to the flange for all of the bottom panel. 2) Method to Apply Tapes a) The sealing tape should be applied to all assembled flange surfaces. b) The centre side of the sealing tape should be overlapped by about 50mm (as shown in the below photo ) 3) To assemble a bottom panel block, fIrst connect several bottom panels into a sub-block. Determine the block size according to the site condition, the work space, number of workers, use or non-use of a crane, etc. A block that is too large cause difficulty in relocation and other work. Therefore, it is recommended that one block be limited to 10 panels x 2rows. 4) Arrangement and type of bottom panels. Place bottom panels one by one upside (as shown in Fig. 2). When installing a drain nozzle, place a pit panel in the pre-determined position. 5) Assembly of Drain Panel Using a hole saw(for a small bore),and a jigsaw(for large bore), th

Check steel skid base

Image
Check steel skid base Basic structure of steel footing is the cross-hatched type. A) Standard of Steel Skid Per Height B) Assembling for Steel Skid 1) All bolts/nuts for connecting steel skid shall be M14 X 40 ℓ. 2) Joint Angle( or Channel) at intervals of 1M using base frame 3) Put Angle(or Channel) on base PAD and joint using ㄱtype Bracket (7575Z) DAEJOO ENG. CO.,LTD ​ Sky Seo (Managing Director) Website : www.daejoosmc.com Blog1 :  grp-water-tank.blogspot.com Blog2 :  blog.naver.com/biotank420 E-mail : biotank420@gmail.com Managing Director's Mobile / Whatsapp : +82-10-2758-7147 General Manager's Mobile / Whatsapp : +82-10-7741-8555