1. Check Concrete Foundation

2. Check Steel Skid Base

3. Assembly of Bottom Panel Block

4. Setting of Bottom Panel block onto Steel Skid Base

5. Assembly of Side Panel Block

6. Assembly of Roof Panel Block

7. Installation of Roof Panel Block Support Pole

8. Installation of Internal Ladder

9. Nozzle Installation

10. Installation of External Ladder

11. Installation of Anchor Bolts